Chennai Metro : Soil tests are on in Luz, Alwarpet

Chennai Metro contractors have begun soil testing work on TTK Road, Alwarpet and on Luz Church Road.

Just now, the work is on at three places on TTK Road.

This is carried out as a part of the corridor 4 of Chennai Metro rail’s phase 2 project.

The corridor 4 from Lighthouse to Poonamallee will pass through San Thome – Kutchery Road – Thirumayilai Metro – Alwarpet – Bharathidasan Road – Adyar Gate Jn.

Recently, the residents of Alwarpet held a second meeting to debate the implications of the Metro project.

Some large stores in Luz / Alwarpet are making plans to move to a new location; Palam Silks on Luz Church Road has opened a new store on Musiri Road.

This entry was posted on Tuesday, May 14th, 2019 and is filed under Chennai Metro, Civic. You can follow any responses to this entry through the RSS 2.0 feed. You can skip to the end and leave a response. Pinging is currently not allowed.